Critical power upgrades for live data centres and critical sites.

Replacing or modifying UPS, generators and switchgear takes more than competent installation. The change has to be planned around the live operation, with interfaces, isolations, risk, commissioning and handover controlled throughout.

UPS & battery  •  Generators  •  Switchgear  •  Live-site commissioning
The challenge

Keeping the lights on while the kit changes.

Ageing or changing critical power inside a site that cannot go offline.

UPS batteries are typically replaced every five to seven years, and each replacement has to fit around customer load and maintenance windows. Generator and switchgear changes carry the same constraint: the operation stays live while the kit comes out.

Primus is set up for this: a named senior lead, a method agreed with the site team before any work starts, and controls on every change through to commissioning and handover.

The operation stays live while the kit comes out.
Method

How Primus controls delivery.

Seven stages. Same discipline on every project.

Stage 01
→

Site survey

Walk the site with the operations team. Understand resilience, load, access and the operation around the kit.

Stage 02
→

Agreed methodology

Write the method with the client, not for them. Isolations, interfaces and sequence approved before work starts.

Stage 03
→

Isolation strategy

Define every isolation point, who owns the switch, what proves it dead, how it goes back live.

Stage 04
→

Project controls

Programme, risk register, change log and progress reporting on the client’s terms.

Stage 05
→

Change management

Every variation to method or scope approved against impact on the live site before it happens.

Stage 06
→

Commissioning

Witnessed tests against the agreed criteria. No step signed off without evidence.

Stage 07
→

Handover

Clean, complete, documented handover with O&M, test records and operational briefings.

Technical scope

What we deliver.

Three overlapping disciplines, delivered to one standard.

UPS & battery replacement

Generator replacement

Switchgear upgrades

FAQs

What buyers ask first.

In most resilient configurations, yes. Load is held on the remaining UPS or a temporary supply while one unit is isolated and replaced, under a method agreed with the site team.

Typically every five to seven years, depending on battery type, temperature and load.

Outcomes

Project evidence, not promises.

Outcomes are added as each client-approved case study is signed off. Metrics, images and references come from the project team, not the brochure.

Next step

Discuss a critical power project.

Share scope, resilience and site constraints. We will come back with a method and sequence.